  • 1.  MM02 Costing 1 View MBEW-ZPLD1 Planned price date 1

    Posted 03-26-2019 08:12
    ​​Hello Folks

    I am recording the the transaction MM02 an trying to upload the planned price information. Normally it should not be that difficult, even for a newbie like me, but the recording session seems to have trouble catching the field MBEW-ZPLD1.

    The error message shows that the planned priced date is deactivated or neither exist in Dynpro 4000, but it is not the case.

    Did anyone encountered a similar problem?

    Have a great day out there.... :-)

    Jean-Pierre



    ------------------------------
    Jean-Pierre Greiner | Head of SAP CC
    Gilgen Door Systems AG | +41 31 734 44 33
    ------------------------------


  • 2.  RE: MM02 Costing 1 View MBEW-ZPLD1 Planned price date 1

    Posted 03-27-2019 08:36
    Hi Jean,
    I am not mulch help to you. I am able to pull in the date field when I record. 
    Do you have MM full access? My background is Material master. 

    Hope this can be of some help.

    ------------------------------
    Benjamin Kielas | SAP Master Data Team Lead
    Generac Power Systems, Inc. | (262) 544-4811
    ------------------------------



  • 3.  RE: MM02 Costing 1 View MBEW-ZPLD1 Planned price date 1

    Posted 03-27-2019 08:47
    Hi Jean-Pierre,

    You may want to consider using a BAPI (e.g. BAPI_MATERIAL_SAVEDATA). 

    Winshuttle has a good WUGinar showing some examples:
    https://www.winshuttle.com/assets/webinar-wuginar-how-to-use-studio-direct-to-leverage-sap/?mkt_tok=eyJpIjoiTUdObFlqVmtZbVl6Wm1aaCIsInQiOiI5Zm9XSTgrMWJCY095T0VBc09KNzRVaXlBTlZyR1c1XC9pXC9oQ1l3WWE4MkhCeTJKU09vRkxHU1Y5T0VyTkxUaGVMRG5BYmU3YkZBYkhhTGgrcGhoa2VRY3pPMFdyT2FFa0trdVpUSGtyVXZvTlJhQzMreklOR0E2OE9PRys5OEFBIn0%3D

    Brian

    ------------------------------
    Brian Mcnally | BA
    Versum Materials | 61-530-5000
    ------------------------------



  • 4.  RE: MM02 Costing 1 View MBEW-ZPLD1 Planned price date 1

    Posted 03-27-2019 08:58
    Can you change that field in MM02 in SAP(not in Winshuttle) in whatever client you are recording in? 

    I have had issues where my authorizations were different in QAS and PRD and caused odd things to happen.  

    I have a script that updates this field, it worked fine without having to resort to using BAPIs.

    ------------------------------
    Michael Shaw | Master Data Analyst
    Southeastern Mills, Inc. | 706-291-6528
    ------------------------------



  • 5.  RE: MM02 Costing 1 View MBEW-ZPLD1 Planned price date 1

    Posted 03-27-2019 12:58
    I agree with Michael...if the field is not activated when recording the script it is very likely an authorizations issue.  I also have a Winshuttle script which updates planned price, there should be no need to use BAPIs.