hi,
I've changed the recording
before I did it like, add all periods on 1 screen, when the screen was full, I entered the periods on the next screen

I've changed this, first I go to the end of the screen , and then on the last line I add the period + then I got the message, enter again, then entry goes to the top, then I enter the new period , one by one... until every period is entered


this has solved my issue.
I hope this is clear for you ?
kristel
------------------------------
Kristel Smeyers | SAP Specialist
Cartamundi | +3214445944
------------------------------
Original Message:
Sent: 10-13-2022 08:18
From: jan ketele
Subject: md61 script does not work properly
Hi Kristel, what change did you apply to resolve that issue ?
mvg, Jan
------------------------------
jan ketele | release expert
Xeikon Manufacturing NV | +3234431875
Original Message:
Sent: 10-12-2022 15:54
From: Kristel Smeyers
Subject: md61 script does not work properly
hi, I changed recording, and now it seems to work
------------------------------
Kristel Smeyers | SAP Specialist
Cartamundi | +3214445944
Original Message:
Sent: 10-12-2022 08:36
From: Kristel Smeyers
Subject: md61 script does not work properly
hi,
I've created a script for MD61, adding forecast to materials for 18 periods in future.
first I delete the periodes, this works, then creation of periods should start.
I've noticed that sometimes I got a warning message and then the first 6 periods are not created.
is there anyone who knows how to avoid this ?
when I ran in debug I got this message, planning period should lie in the future - normally I've got this message also during recording, but it seems that winshuttle is not always skipping these message (when I got the message, I pushed entered, and then winshuttle should continue)

attached, you can find the script and excel
------------------------------
Kristel Smeyers | SAP Specialist
Cartamundi | +3214445944
------------------------------